-
DESTINATION MOON: A History of the
Lunar Orbiter Program
-
-
- CHAPTER V: IMPLEMENTING THE
PROGRAM
-
- Early Funding
Considerations
-
-
-
- [97] The beginning of
the Lunar Orbiter Program's next stage was hardly noticed in the
turbulent atmosphere in which the U.S. space program existed at
home and abroad. Congress was questioning NASA and JPL about
apparent poor management in the Ranger Program, while the first
manned Gemini flight, scheduled for launch late in 1964, was
experiencing setbacks. Everywhere, it seemed, the critics of
America's space exploration efforts were finding fault with NASA.
They pointed to Soviet manned and unmanned space accomplishments
and asked why the United States was not keeping pace. In the midst
of these inauspicious circumstances, the fledgling Lunar Orbiter
Program at Langley nevertheless got off to a promising
start.
-
- Four aspects of the new program became
important during the twelve months that followed the signing of
the contract: 1) funding; 2) spacecraft design; fabrication,
testing, and integration with the launch vehicle.; 3) mission
design; and 4) the establishment of schedules and working
relationships between the various NASA centers and the
contractors. Once the definitive contract with Boeing had been
approved, funding problems became more Complex. They constituted
one of the dominant [98] constraints
defining the flow of activities during the entire course of the
program. A brief description of funding through the end of 1964
will illustrate the problem.
-
- Beginning in February 1964 the Office of
Space Science and Applications had decided to commit to Lunar
Orbiter the full $20 million which Congress had appropriated for
FY 1964 specifically for an orbiter. However, the negotiated
contract of April 16 obligated NASA to provide Boeing with funds
as it required them, if the contractor was to be held to the
incentive provisions in the contract. This meant that NASA had to
establish and maintain a minimum funding rate to avoid schedule
lags. Although NASA committed the FY 1964 funds, the Lunar Orbiter
Program faced a new situation in FY 1965, beginning July 1, 1964.
During the contract talks Boeing had predicted an expenditure rate
of $26.1 million for that fiscal year, but by May this sum had
increased to $37.1 million.1
-
- A detailed PERT revealed one reason for
this sudden rise. It found that by compressing the development
phase of the program, NASA could gain more time for the testing
phase. Acceleration of development, however, would require a
higher funding rate than Langley or Headquarters had originally
anticipated.
-
- [99] Realizing this
the Office of Space Science and Applications released a guideline
of $31.5 million for FY 1965 to the Langley Research Center in the
spring of 1964. Of this Boeing would spend $28.9 million. Langley,
on the other hand, had requested $39.1 million, of which Boeing
was to spend $37.1 million. OSSA preferred to remain conservative,
waiting until Boeing could supply more accurate, concrete
information on funding needs before making a decision to increase
the funding rate. Oran W. Nicks, Director of Lunar and Planetary
Programs within OSSA, felt that the Lunar Orbiter funding
requirements could increase at an uncomfortably fast pace and thus
compromise other projects within OSSA.
-
- Costs data for the Lunar Orbiter Program
during the first quarter of the project, ending June 30, 1964,
revealed that actual costs had exceeded estimated costs by $1.1
million. The estimated costs had been made by the Boeing Company
on April 30, and the difference between the two constituted an
underestimate by Boeing of 45% for the
quarter.2
-
- Throughout the summer of 1964 the rate of
expenditure at Boeing remained Langley's single greatest headache.
This was almost entirely due to Boeing's failure to sign
[100]
the two major subcontractors, Eastman Kodak and RCA, to definitive
contracts. Floyd L. Thompson kept Nicks informed of the funding
problem during the summer months, and in August Nicks requested
Thompson to review the entire funding situation and its potential
impact on other programs.3
-
- The scope of the funding problem revealed
the need for closer cooperation between Langley and NASA
Headquarters. Both organizations sent representatives to an August
19 meeting at Langley to examine and resolve their differences and
strengthen the coordination of policies pertaining to Lunar
Orbiter.4 At the meeting officials from the various Langley
offices connected with Lunar Orbiter gave detailed presentations
of their work and requested further support of clarification of
policies pertaining to the program.
-
- Headquarters people made it clear that
they wished to establish much firmer ties with Langley to ensure a
better request-response relationship throughout the program.
Langley people expressed concern that they had had to make
decisions without the help of such useful tools as complete
monthly funding reports from Headquarters which they could
[101]
use to gauge their expenditure flow.5
-
- Another pressing matter aired at the
meeting was Langley's desire to fund Boeing three months in
advance. This would allow enough flexibility to keep hardware
procurement from falling behind schedule. But, because of the
acceleration of development during the tight money situation in FY
1965, Langley's request appeared to be out of the question. Even
with the present funding plan, funding to Boeing tended toward a
minimum below which it could not go without precipitating serious
schedule changes.
-
- Langley and Headquarters officials decided
to establish a minimum level for total expenditures at $41 million
for fiscal 1965.6 Cost reduction appeared unlikely in every program
area except the Air Force Support Services at the Boeing Company.
Here, according to Nicks, the very high projected cost figure of
$2.45 million for FY 1965, which Langley's August Program
Operating Plan had forecast, might be subject to reduction. In FY
1964 the U.S. Air Force had charged NASA an expensive 6% of
Langley's combined contract costs as the fee for its support. NASA
wanted the more reasonable rate of 1% to 2% which it received from
the Navy and the Army for their various support services.
-
- [102] Nicks maintained
that if NASA could obtain a figure of 1.5% of the Lunar Orbiter
contract costs for FY 1965 as the rate of charge for USAF support,
then it could, alleviate some of the financial pressure which
limited the flexibility of Lunar Orbiter funding in the coming
fiscal year.7 This new arrangement would have to be worked out
with Air Force representatives.
-
- Meanwhile the participants in the August
19 funding meeting agreed that no contract changes would be made
if the changes would increase funding above the FY 1965 guidelines
or above those laid down in the Project Approval Document or above
the total program guidelines, unless the Lunar Orbiter Program
Office in Washington had subjected the proposed changes to the
most thorough scrutiny.8
-
- The fact that the bulk of the procurement
and development expenditures would come in FY 1965 further clouded
the Lunar Orbiter funding situation. This reality placed a strict
constraint on administration of the incentive contract with
Boeing; it also prompted Langley Director Floyd L. Thompson to
comment that, "if we aren't prepared to play table stakes, we
shouldn't be in the incentive poker [103]
game."9 To this Scherer added that, "when the government
asks a contractor to assume the risk of an incentive contract, it
must assume itself the responsibility for funding the contractor
as he needs it."10 He named the figure of $41.8 million as the
rock-bottom minimum for the program in FY 1965 and stressed that
any slip below this would cause schedules to lag and force basic
alterations in the contract.
-
- Lunar Orbiter funding became very tight in
September at the time when Boeing was beginning to negotiate final
contracts with Eastman Kodak and RCA. Langley informed NASA
Headquarters that Boeing had received quotations from Eastman
Kodak and RCA and, starting on September 14, would begin contract
negotiations.11 The original costs for the photographic system,
which Boeing had quoted to Langley officials, proved to be much
lower than the price at which Eastman Kodak was willing to deliver
the subsystem for the spacecraft. This, in turn, had slowed
contract talks between the two firms.
-
- Scherer's main concern about the funding
situation centered upon his recognition that to allow the program
[104]
to fall behind schedule because of too stringent funding would be
tantamount to erasing the advantages of the incentive contract. If
NASA induced the contractor to lose confidence in the contract
because of a necessity to renegotiate part or all of it because of
NASA niggardliness, then the program's overall success would be
jeopardized. But NASA Headquarters remained steadfast in its
retention of the $41.8-million FY 1965 funding minimum, even
though Langley had called for $45.9 million.12
-
- The growing seriousness of this problem
brought Headquarters and Langley officials together on September
9. They established a new funding level based upon the increased
requirements of Lunar Orbiter. This raised the original $94.6
million figure for the FY 1965-FY 1966 period to $105
million.13 The new ceiling offered Langley greater flexibility
and reassured the Lunar Orbiter Program Office in Washington that
the incentive provisions of the Boeing contract would be
maintained.
-
- Both Langley and Headquarters concurred in
the policy of holding all contract and schedule changes to the
barest minimum. Moreover, both undertook studies of their
[105]
operations to determine where costs might be reduced, and by the
end of 1964 they had succeeded in pinpointing several ways to save
more money. Scherer summarized the areas where cost reductions
seemed most feasible and sent a report to Clifford H. Nelson at
Langley at the end of December.
-
-
-
-
-
-
-